The table shows some information about the time, in seconds, taken by group A to complete a logic puzzle.
| Minimum | Lower Quartile | Median | Upper Quartile | Maximum |
|---|---|---|---|---|
| 22 | 35 | 48 | 62 | 85 |
Draw a box plot for this information.

The box plot below shows the distribution of the times taken by group B to complete the same puzzle.

Compare the distribution of the times taken by group A and group B.
Practise Eduqas GCSE Maths Box Plots with exam-style questions for Foundation and Higher tier. 36 questions, matched to the Eduqas GCSE Maths (C300QS) specification and written in Component 1 and Component 2 style. Every question includes a full worked solution and mark scheme, so you can see where marks are awarded rather than just whether you got the answer right.