Question 14
Easy

An industrial steel plant is evaluating two low-carbon technologies for a new production facility: an Electric Arc Furnace (EAF) and a Green Hydrogen-ready Shaft Furnace.

The table below shows some specifications and operational costs for each furnace type:

FeatureElectric Arc Furnace (EAF)Green Hydrogen-ready Shaft Furnace
Batch cycle time (minutes)18045
Energy cost per 10 tonnes of steel produced (£)450950
Maximum capacity per batch (tonnes)85130
Capital installation cost (£ millions)1829

Evaluate the advantages and disadvantages of choosing the Green Hydrogen-ready Shaft Furnace rather than the Electric Arc Furnace (EAF) for their operation.

[4]