Skip to content
MathsGenie logo
Quick links
Open app

Course home

  1. A Level
  2. Maths CCEA
  3. Question bank

4.5 Statistical distributions (A-level only)

EasyMediumHard
12345678910111213141516171819202122232425262728293031323334353637383940414243444546474849505152535455565758596061626364656667686970717273
Question 70

The completion times for three distinct phases of a luxury residential construction project—foundation preparation (FFF), structural framing (GGG), and interior finishing (HHH)—are assumed to follow independent normal distributions:

F∼N(40,4.52) F \sim \text{N}(40, 4.5^2) F∼N(40,4.52) G∼N(60,7.22) G \sim \text{N}(60, 7.2^2) G∼N(60,7.22) H∼N(35,6.42) H \sim \text{N}(35, 6.4^2) H∼N(35,6.42)

where the times are measured in working days.

a.

Determine the probability that the total time required for these three phases in a randomly selected project exceeds 150 working days.

[3]
b.

Find the probability that the structural framing phase takes at least 30 days longer than the interior finishing phase.

[3]
c.

Given that P(F+G+H<t)=0.05P(F + G + H < t) = 0.05P(F+G+H<t)=0.05, find the value of ttt.

[2]
d.

A construction firm is overseeing 8 independent projects of this type. Using the probability calculated in part (a), find the probability that the total time for the three phases exceeds 150 working days in at least two of these 8 projects.

[3]
e.

An analyst suggests that the assumption of independence between F,G, F, G,\,F,G, and H H\,H within a single project is likely flawed. Explain, with a reason, whether this suggests the model used in part (d) is appropriate.

[1]

4.5 Statistical distributions (A-level only) Questions

  1. A Level
  2. /Maths
  3. /4.5 Statistical distributions (A-level only)