A manufacturing city is supplied with electricity from a distant wind farm. To make the transmission of electrical energy as efficient as possible, which level of voltage should be used in the long-distance cables, and which device should be installed at the wind farm before the power enters the grid?
High voltage, step-up transformer
High voltage, step-down transformer
Low voltage, step-up transformer
Low voltage, step-down transformer
136 exam-style questions on CIE IGCSE Physics 4.5.6a Construction and operation of a transformer. Each one has a worked solution and a mark scheme showing where the marks go.