Question 10

An offshore tidal-stream turbine array generates electrical power that must be transmitted to an onshore coastal substation via a long subsea cable. Before transmission, a step-up transformer at the offshore platform increases the potential difference to 132 kV132\text{ kV}132 kV.

Explain how transmitting the electrical power at this high potential difference minimizes energy dissipation in the subsea cable.

[2]