Question 26

An electric cable system moves a piece of stage scenery in two sections along a straight track. The force from the cable acts along the track.

In the first section, the cable exerts a force of 320 N over a distance of 6.0 m. The total work done by the cable over both sections is 4200 J.

In the second section, the scenery moves 9.5 m.

Calculate the force exerted by the cable in the second section.

[3]