Skip to content

Course home

Direct and Inverse Proportion

Direct and Inverse Proportion

EasyMediumHard
123456789101112131415161718
Question 4

It takes 4 painters 3 days to complete a job.

Work out how many days it would take 2 painters to complete the same job.

[2]
Markscheme

Direct and Inverse Proportion Questions

  1. GCSE
  2. /Maths
  3. /Direct and Inverse Proportion

189 exam-style questions on Eduqas GCSE Maths Direct and Inverse Proportion. Each one has a worked solution and a mark scheme showing where the marks go.

Question bank