123456789101112131415161718192021222324252627282930313233343536373839404142434445464748495051525354555657585960616263646566676869707172737475767778798081828384858687888990919293949596979899100101102103104105106107108109110111112113114115116117118119120121122123124125126127128129130131132133134135136137138139140141142143144145146147148149150151152153154155156157
Question 91

Machines A, B and C produce 20%, 45% and 35% of a factory's output. The fault rates for A and B are 3% and 5%. The overall fault rate is 4%.

Find the fault rate for machine C.

[4]