Question 43

The time required to manufacture a high-precision gear using a CNC machine is modeled by a normal distribution with a mean of 150 minutes and a standard deviation of 12 minutes.

There are 5 gears currently in the queue to be processed by this machine.

Making a reasonable assumption about the processing times for these gears,

a.

find the probability that the total time taken to process the 5 gears will be more than 13 hours.

[4]
b.

State the assumption you have made in part (a).

[1]
c.

A semi-automated lathe is also available at the facility. The time required for a gear to be processed on the lathe is modeled by a normal distribution with a mean of 105 minutes and a standard deviation of 10 minutes.

A production manager must decide whether to add a new order to the queue of 5 gears at the CNC machine or to a queue of 7 gears at the semi-automated lathe.

Using a similar assumption to that made in part (a),

find the probability that the total time taken for the 5 gears at the CNC machine will be less than the total time taken for the 7 gears at the semi-automated lathe.

[5]
Markscheme

3.2 Finding Probabilities for Normal Distributions Questions

  1. A Level
  2. /Maths
  3. /3.2 Finding Probabilities for Normal Distributions

80 exam-style questions on Edexcel A Level Maths 3.2 Finding Probabilities for Normal Distributions. Each one has a worked solution and a mark scheme showing where the marks go.

Question bank