123456789101112131415161718192021222324252627282930313233343536373839404142434445464748495051525354555657585960616263646566676869707172737475767778798081828384858687888990919293949596979899100101102103104105106107108109110111112113114115116117118119120121122123124125126127128129130131132133134135136137138139140141142143144145146147148149150151152153154155156157158159160161162163164165166167168169170171172173174175176177178179180181182183184185186187188189190191192193194195196197198199200201202203204205206207208209210211212213214215216217218219220221222223224225226227228229230231232233234235236237238239240241242243244245246247248249250251252253254255256257258259260261262263264265266267268269270271272273274275276277278279280281282283284285286287288289290291292293294295296297298299300301302303304305306307308309310311312313314315316317318319320321322323324325326327328329330331332333334335336337338339340341342343344345346347348349350351352353354355356357358359360361362363364365366367368369370371372373374375376377378379380381382383384385386387388389390391392393394395396397398399400
Question 157

The completion times for three distinct phases of a luxury residential construction project—foundation preparation (FFF), structural framing (GGG), and interior finishing (HHH)—are assumed to follow independent normal distributions:

F∼N(40,4.52) F \sim \text{N}(40, 4.5^2) F∼N(40,4.52) G∼N(60,7.22) G \sim \text{N}(60, 7.2^2) G∼N(60,7.22) H∼N(35,6.42) H \sim \text{N}(35, 6.4^2) H∼N(35,6.42)

where the times are measured in working days.

a.

Determine the probability that the total time required for these three phases in a randomly selected project exceeds 150 working days.

[3]
b.

Find the probability that the structural framing phase takes at least 30 days longer than the interior finishing phase.

[3]
c.

Given that P(F+G+H<t)=0.05P(F + G + H < t) = 0.05P(F+G+H<t)=0.05, find the value of ttt.

[2]
d.

A construction firm is overseeing 8 independent projects of this type. Using the probability calculated in part (a), find the probability that the total time for the three phases exceeds 150 working days in at least two of these 8 projects.

[3]
e.

An analyst suggests that the assumption of independence between F,G, F, G,\,F,G, and H H\,H within a single project is likely flawed. Explain, with a reason, whether this suggests the model used in part (d) is appropriate.

[1]
Markscheme

The Normal Distribution Questions

  1. A Level
  2. /Maths
  3. /The Normal Distribution

616 exam-style questions on Edexcel A Level Maths The Normal Distribution, covering 3.1 The Normal Distribution, 3.2 Finding Probabilities for Normal Distributions, 3.3 The Inverse Normal Distribution Function, 3.4 The Standard Normal Distribution, 3.5 Finding the mean and standard deviation, 3.6 Approximating a Binomial Distribution, and 3.7 Hypothesis Testing with the Normal Distribution. Each one has a worked solution and a mark scheme showing where the marks go.

Question bank