Card 1 of 24
In CPA, what does a dependency mean for when an activity can begin?
A
It can begin immediately when the required previous activity starts.
B
It cannot begin until the required previous activity is complete.
C
It can begin independently of whether the previous activity is complete.
D
It must be completed before the required previous activity can begin.
Card 1 of 24
Critical Path Analysis Flashcards
24 flashcards on Edexcel A Level Business Critical Path Analysis: the key terms, formulae and case studies you need to recall for Paper 1, Paper 2 and Paper 3.